task #9862: Setup automated FTP uploads

Submitted by:  Rodrigo Rodrigues da Silva <pitanga>
Submitted on:  Wed 04 Nov 2009 03:55:43 AM UTC  
 
Should Start On: Sun 28 Feb 2010 11:00:00 PM UTCShould be Finished on: Wed 31 Mar 2010 10:00:00 PM UTC
Category: NonePriority: 5 - Normal
Status: In ProgressPrivacy: Public
Percent Complete: 0%Assigned to: Rodrigo Rodrigues da Silva <pitanga>
Open/Closed: OpenEffort: 0.00

Mon 22 Feb 2010 09:53:17 PM UTC, comment #1:

I've assigned myself this task, and set its status to "in progress".

Probably the actual uploading must be done by a project administrator, but i can try and see what happens. If i don't succeed, i will re-assign this back to pitanga.

Aside from administrative issues, the most important thing is to have something presentable to upload! Towards this end, i've set the task timeframe (start/end dates) to be march 2010. I think it's a reasonable goal to be able to get an alpha release out in three or four weeks.

Thien-Thi Nguyen <ttn>
Project Member
Wed 04 Nov 2009 03:55:43 AM UTC, original submission:

Check http://www.gnu.org/prep/maintain/html_node/Automated-FTP-Uploads.html.

Rodrigo Rodrigues da Silva <pitanga>
Project AdministratorIn charge of this item.

 

No files currently attached

 

Depends on the following items: None found

Items that depend on this one: None found

 

Carbon-Copy List
  • -unavailable- added by ttn (Posted a comment)
  • -unavailable- added by pitanga (Submitted the item)
  •  

    Do you think this task is very important?
    If so, you can click here to add your encouragement to it.
    This task has 0 encouragements so far.

    Only logged-in users can vote.

     

    Please enter the title of George Orwell's famous dystopian book (it's a date):

     

     

    Follow 6 latest changes.

    Date Changed By Updated Field Previous Value => Replaced By
    Mon 22 Feb 2010 11:02:14 PM UTCttnAssigned tottn=>pitanga
    Mon 22 Feb 2010 09:53:17 PM UTCttnShould Start OnWed 04 Nov 2009 02:00:00 AM UTC=>Sun 28 Feb 2010 11:00:00 PM UTC
      Should be Finished onWed 04 Nov 2009 02:00:00 AM UTC=>Wed 31 Mar 2010 10:00:00 PM UTC
      Priority1 - Later=>5 - Normal
      StatusNone=>In Progress
      Assigned toNone=>ttn