task #12684: setup ET - the EiffelTest continuous integration system

Submitted by:  Cyril Adrian <cadrian>
Submitted on:  Fri Jun 7 11:46:26 2013  
 
Should Start On: Thu Jun 6 22:00:00 2013Should be Finished on: Tue Aug 6 22:00:00 2013
Category: ETPriority: 5 - Normal
Status: In ProgressPercent Complete: 40%
Assigned to: Raphael Mack <ramack>Open/Closed: Open
Fixed Release: NonePlanned Release: curtiss
Effort: 0.00

Tue Oct 15 18:46:43 2013, comment #1:

these are cool features, but not blocking for adler, so let's shift this to bell (at least)

Raphael Mack <ramack>
Project AdministratorIn charge of this item.
Fri Jun 7 11:46:26 2013, original submission:

https://github.com/LibertyEiffel/Liberty/issues/30

basically ET is working, but I want to

  • display statistics (runtime of each stage, #warn #ok and #fail)
  • send an email to the commits author (email taken from github) in case the state changed
Cyril Adrian <cadrian>
Project Administrator

 

No files currently attached

 

Depends on the following items: None found

Items that depend on this one: None found

 

Carbon-Copy List
  • -unavailable- added by ramack (Updated the item)
  • -unavailable- added by cadrian (Submitted the item)
  •  

    Do you think this task is very important?
    If so, you can click here to add your encouragement to it.
    This task has 0 encouragements so far.

    Only logged-in users can vote.

     

    Please enter the title of George Orwell's famous dystopian book (it's a date):

     

     

    Follow 4 latest changes.

    Date Changed By Updated Field Previous Value => Replaced By
    Tue Jan 5 20:39:15 2016ramackPlanned Releasebell=>curtiss
    Tue Oct 15 18:46:43 2013ramackPlanned Releaseadler=>bell
    Sat Jun 8 11:14:23 2013ramackShould be Finished onThu Jun 6 22:00:00 2013=>Tue Aug 6 22:00:00 2013
    Sat Jun 8 11:14:07 2013ramackPercent Complete0%=>40%